Brunei LNG (BLNG) Plant

Location:Darussalam (Brunei) Plant Capacity: 6.71 MT/year

  

IPS System Migration (March 2012 - Aug 2012 & Apr 2013 - Dec 2013)

  • The job included to complete the documents of detailed engineering of every upcoming batches, conducting FAT, and carryout the necessary activities before, during and after the shutdown including SAT signoff

FEED for the Plant IPS System Migration (Aug 2011 - Oct 2011)

  • Job was to constitute the proposal for the upgrade of 29 FSC System cabinets, in different batches to the available current latest technology, i.e., the latest FSC Navigator (R710.1) and SOE software (R141).